Jasper Courthouse Square Update: March 24th, 2023

Jasper- There is an update on the ongoing Courthouse Square and Revitalization project in Jasper.
  • Construction crews continue make progress in the NW quadrant of the Square. Schedule includes base paving the week of April 10th.
  • Storm sewer installation is complete.
  • Concrete crews are installing sidewalks, planters, and curbs. The fire pit foundation is being built. Pavers and sprinklers to be installed in coming weeks.
  • Concrete work  on the alley north of the Astra Theatre in the SW quadrant is underway. Steps to be poured by the end of March.
  • Courthouse lawn (north section) to be installed in the next three weeks.
  • Board of Public Works to consider approval of new parking spaces along west side of Jackson Street near intersection with 6th Street at an upcoming meeting. Travel lanes planned to be reduced to two lanes.
  • The schedule will continue to be contingent on weather and supply factors.
  • The parking lot adjacent to City Hall remains available for 2-hour public parking.
  • Foot traffic and accessibility to building entrances will be maintained at all times.
  • The next meeting with contractor representatives is Wednesday, April 5th.

For specific construction questions, please contact the City of Engineering Department at 812-482-4255.