Downtown Revitalization Project Phase II Update 3.5.2025

A construction meeting was held on March 5th for the Downtown Revitalization Phase II Project, involving Ragle Construction, REA, VS Engineering, and the City of Jasper.

Crews will continue pouring curbs, ADA ramps, and sidewalks between 3rd and 4th Streets, with road closures expected to last until mid-March. Additionally, intermittent lane closures are planned on 3rd Avenue at Main Street as work progresses.

Starting the week of March 17th, construction will move to Main Street between 7th and 9th Streets, with expected completion in Spring 2025. The work will begin between 7th and 8th Streets, with both blocks anticipated to remain closed for much of the project.

The schedule is weather and materials-dependent, but accessibility to all building entrances will remain for foot traffic throughout. Bi-weekly meetings and updates will keep the community informed as the project moves forward.