Courthouse Square Infrastructure and Revitalization Update: February 16th
Jasper- A few updates on the Courthouse Square Infrastructure & Revitalization Project from the meeting with the construction team this morning.
- Construction crews continue to grade and prepare subgrade for the curb and concrete work in the NW quadrant.
- Storm sewer installation continues.
- Prep for sidewalks, planters, and the fit pit is underway.
- Also some work is being completed in the NE quadrant: installation of swings and signage being next.
- Parking is now open in the NE quadrant.
- The schedule will continue to be contingent on weather and supply factors.
- The parking lot adjacent to City Hall remains available for 2-hour public parking.
- Foot traffic and accessibility to building entrances will be maintained at all times.
- The next meeting with contractor representatives is Wednesday, March 1st.
For specific construction questions, please contact the City of Engineering Department at 812-482-4255.